WRIGHT-PIERCE =
Engineering a Better Environment PROJECT MEMO
TO: Nashua PS Upgrade Project Team DATE: 4/20/2021
FROM: M. Patrick PROJECT NO.: 20028A
SUBJECT: Nashua PS Change Order No. 2 Summary
The purpose of this memo is to summarize Change Order No. 2. This will be handled as a partial
balancing change order. There are several components of this change order, summarized below:
Item
No. Description of Items Add / Deduct
1 Newton — Electrical Modifications $ 27,335.18
Item 9 — Misc Concrete (balancing order) $ ($100.00)
3 Final Completion Time Extension $ 36 days
Net Contract Price Increase of this Change
Order (CO-02): $ 27,235.18
*/t is noted the Defelice’s Direct Labor costs are based on a 33% burden rate.
Below is a summary of each change order. Attached after this memo is the backups
provided by Defelice for the costs associated with each change order.