Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/19/2021 - P18

Finance Committee - Agenda - 5/19/2021 - P18

By dnadmin on Mon, 11/07/2022 - 13:40
Document Date
Fri, 05/14/2021 - 13:59
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/19/2021 - 00:00
Page Number
18
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051920…

WRIGHT-PIERCE =

Engineering a Better Environment PROJECT MEMO
TO: Nashua PS Upgrade Project Team DATE: 4/20/2021
FROM: M. Patrick PROJECT NO.: 20028A

SUBJECT: Nashua PS Change Order No. 2 Summary

The purpose of this memo is to summarize Change Order No. 2. This will be handled as a partial
balancing change order. There are several components of this change order, summarized below:

Item
No. Description of Items Add / Deduct
1 Newton — Electrical Modifications $ 27,335.18
Item 9 — Misc Concrete (balancing order) $ ($100.00)
3 Final Completion Time Extension $ 36 days

Net Contract Price Increase of this Change
Order (CO-02): $ 27,235.18

*/t is noted the Defelice’s Direct Labor costs are based on a 33% burden rate.

Below is a summary of each change order. Attached after this memo is the backups
provided by Defelice for the costs associated with each change order.