Jim Donchess
Mayor e City of Nashua
To: Board of Aldermen
From: Mayor Jim Donchess
Date: May 26, 2021
Re: Contract in Excess of $1M Award — Sewer Replacement Program Change Order #3
Pursuant to NRO: § 5-74/B: E. Approval by the Finance Committee of a contract award in excess of
$1,000,000 shall be submitted to the full Board of Aldermen at its next regularly scheduled meeting
for final approval prior to award of the contract.
The Finance Committee has approved and placed on file the notification of the award of the
referenced contract at the June 2, 2021 meeting and as such | am requesting the full Board of
Alderman approve the following contract:
Item: Change Order #3 to the 2020 Sewer Replacement Program
Value: $1,300,000
Vendor: SUR Construction West of Winchester NH
Purchasing Memo#: 21-135 dated May 25, 2021
Contract Term:
Thank you.
229 Main Street * PO Box 2019 * Nashua, New Hampshire 03061-2019
603.589.3260 * fax 603.594.3450 * NashuaMayor@NashuaNH.gov
www. NashuaNH.gov