Flashing over the field splice intersection.
FLASHING
A. Wall and curb flashing shall be cured EPDM membrane. Continue the deck membrane as wall flashing
where practicable. Use Pressure-Sensitive Curb Wrap when possible to flash curb units.
B. Follow manufacturer’s typical flashing procedures for all wall, curb, and penetration flashing including metal
edging/coping and roof drain applications.
WALKWAYS
A. Install walkways at all traffic concentration points (such as roof hatches, access doors, rooftop ladders, etc.)
and all locations as identified on the specifier’s drawing.
B. Adhere walkways pads or rubber pavers to the EPDM membrane in accordance with the manufacturer’s
specifications.
DAILY SEAL
A. On phased roofing, when the completion of flashings and terminations is not achieved by the end of the work
day, a daily seal must be performed.
CLEAN UP
A. Perform daily clean-up to collect all wrappings, empty containers, paper, and other debris from the project
site. Upon completion, all debris must be disposed of in a legally acceptable manner.
B. Prior to the manufacturer’s inspection for warranty, the applicator must perform a pre-inspection to review
all work and to verify all flashing has been completed as well as the application of all caulking.
END OF SPECIFICATION