Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$1,497,993.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 6, 2020
Ready for final payment: November 6, 2020
Net changes from previous Change Orders
$975,125
Net change from previous Change Orders
210 days
Contract Price prior to this Change Order
$2,473,118.00
Contract Times prior to this Change Order
Substantial completion: May 4, 2021
Ready for final payment: June 4, 2021
Net Increase (deerease}_ of this Change Order
$1,300,000.00
Net Increase (deerease) of this Change Order
185 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$3,773,118,00 Substantial completion: November 4, 2021
y 4 4) Ready for final payment: December 4, 2021
RECOMMENDED: oe APPROVED:
By OLA - Be
DPW Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: 27MAY24 Date: 5 ] l202 | Date:
2020 Sewer Replacement Project
2 of 2
Change Order #3