THE CITY OF NASHUA “The Gate City"
Administrative Services Division
To: Mayor Donchess
Finance Committee
From: Kim Kleiner, Director of Administrative Services
Cc: John Griffin, CFO
Jennifer Deshaies, Risk Manager
Sue Lovering, City Clerk
David Fredette, Treasurer
Date: July 11, 2021
Subject: RFP0285-081820 City Hall Building Renovations
In September, the Finance committee approved a contract with DL King & Associates in
the amount of $913,343.24 for the renovation of Motor Vehicles, Tax, Assessing and the City
Clerk offices. December 29, 2020 we received approval from the Finance committee for the
following change orders:
Change Order #1 $5,953.59
Change Order #2 $11,538.32
Change Order #3 $9,060.30
Total Approved Project Total - $939,895.45
On April 7, 2021 the Finance committee approved the following changes:
Change Order 4: $18,951.49
Change Order 5: $6,601.48
Change Order 6: ($4,071.70)
Total Approved Project Total - $ 961,376.72
The change orders listed below are the final changes to the project: