D. Make arrangements to provide access to and exposure for entry those manholes within the
study area which are buried, covered or otherwise not readily accessible.
E. Provide free and legal access to all sites of work.
F. Assure the prompt clearance of major blockages or obstructions in the sewer system, if any,
should such clearance be required for performance of the work.
G. Provide the shutdown of certain pump stations, upon prior request, should it become
necessary for the satisfactory performance of the work.
TH. In the absence of any of the assurances indicated above, give Subconsultant release from
responsibility for the performance of the affizcted portions of the work under this Agreement.
VI. TIME OF PERFORMANCE
Subconsultant anticipates initiating fieldwork no later than SEPTEMBER 1, 2021 with all such
fieldwork to be completed JUNE 30, 2023 (to coincide with expiration of amendment#3 of
the CSO Flow monitoring contract with Nashua which is extended year to year thru
6/30/23 subject to annual budget appropriations). All data will be provided to the Client
within 30) days of completion of each field task.
This proposal is valid until December 31, 2021.
FEES
| Item | Description of Tasks Estimayed Unit Total
# | Quantity Cost Cost