City of Nashua
Energy Recovery Upgrades
CHANGE ORDER 8 —- SUMMARY
Change Order 8 is composed of the following items:
1. Lump sum amount of $200,000, which includes:
a. *Compensation for down time experienced during resolution of method to proceed
for supporting generator no. 1, and all other miscellaneous delays.
b. PCO (Proposed Change Order) 18R1- fuel blending skid relocation in the amount of
$17,918.01 (this work is complete),
c. PCO22R1-Piping relocation for generators in the amount of $1,273.56 (this work is
complete).
d. PCO26-Natural Gas Testing in the amount of $6,715.96 (this work is complete).
e. PCO29R1-SCADA HMI Interface-installed SCADA on PLC in generator room in the
amount of $8344.88 (this work is complete).
(Copies of PCO18R1, 22R1, 26 and 29R1 are attached)
*Note that as part of this agreement and compensation sum Methuen will not seek any further
delay charges against the City and in return the City will not seek compensation in the form of
liquidated damages. Methuen further agrees to complete the remaining work as quickly as
possible; a final date of completion has been set, but will be further amended, if needed, due to
circumstances beyond Methuen’s control.