B-6.1
CHANGE ORDER
No. 008
PROJECT: Energy Recovery Upgrade
OWNER: City of Nashua, NH
(Address)
DATE OF ISSUANCE:
CONTRACTOR: Methuen Construction Co., Inc OWNER’s Project No. 1FB0501-091618
CONTRACT FOR: Energy Recovery Upgrade ENGINEER waldron Engineering & Construction, Inc.
at Nashua NH Wastewater Treatment ENGINEER’s Project No. 359.01
9/2,
You are directed to make the following changes in the Contract Documents.
Description; (See attached)
Purpose of Change Order: (See Attached)
Justification: (See Attached)
Attachments: (List documents supporting change) (Summary+PCO-18R1,22R1,26, 29R1)
CHANGE IN CONTRACT PRICE
Original Contract Price
$ 1,787,378.00
CHANGE IN CONTRACT TIME
Original Contract Time
280 (final completion)
(days or date)
Previous Change Orders
3 144,792.27
Net change from previous Change Orders
31
(days)
Contract Price prior to this Change Order
$ 193217027
Contract Time prior to this Change Order
311 (final completion)
(days or date)
Net Increase (Decrease) of this Change Order
$ 200,000.00
Net Increase (decrease) this Change Order
649
(days)
Contract Price with all approved Change Orders
$ 2.132.170.27
Contract Time with all Change Orders
960 (final completion)
(days or date}
This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.
Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that
the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.
RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: Quremy emt _ BY: By: 4esee> By:
0 Eggineer Owner Contractor NHDES
7/30/21 8/2/21
Date Date Date Date