The H.L. Turner Group Inc.
27 Locke Road Goncord, NH 03301 %:603,.228.1122 hiturner.com
Change Order
PROJECT:
Jackson Mills Hydroelectric
TGC Upgrade Project
Nashua, NH
OWNER:
City of Nashua, NH
City Hall
229 Main Street, PO Box 2019
Nashua, NH 03061-2019
TO CONTRACTOR:
Mavel America, Inc.
121 Mount Vernon Street
Boston, MA 02108
Change Order No: 3
Date: August 12, 2021
Architect’s Project No: 5010
Contract for: Supply of Equipment
Contract Dated: July 8, 2020
Summary of Changes:
The supplier of the turbine/generator equipment (Mavel) shall
extend their standard warranty by an additional 12 months. Based
on a ready to ship date of June 30, 2021, the full manufacturer’s
warranty for the purchased equipment shall be in effect up through
January 30, 2025.
The Contract is changed as follows: The dollar amount has increased and time for delivery is not extended.
Not valid until signed by the Owner, Architect and Contractor
The original Contract Sum was $1,271,700
Net change by previously Authorized Change Orders $66,300 (Change Order Nos. 1 & 2)
The Contract Sum prior to this Change Order was $1,338,000
The Contract Sum will be increased by this Change Order No. 3 in the amount of $38,500
The New Contract Sum including this Change Order will be $1,376,500
The Contract Time will be changed by 0 days.
The Final Date for delivery of equipment is September 15, 2022
Architect: The H.L. Turner Group Inc. Contractor: was emenlee) Inc.
om
Owner: City of Nashua, NH
Ap Cee
By;//7 le aliens
By: Paul M. Becht By:
Date: August 12, 2021 Date: Date: August [(F , ZOZ |
/ 7
Change Order #3.docx 5010 lofi