The New Contract Sum including this Change Order will be $1,338,000
The Contract Time will be changed by 397 days.
The Final Date for delivery of equipment per this Change Order is September 15, 2022
Architect: The H.L. Turner Group Inc. Owner: The City of Nashua, NH Contractor: Mavel America, Inc.
By: Paul M. Becht By: By: SEE
Date: August 6, 2021 Date: Date! auaques @ 2021
Change Order #2.docx 5010 2 of2
ARCHITECTS = ENGINEERS = BUILDING SCIENTISTS
©Copyright 2021