The H.L. Turner Group Inc.
27 Locke Road Concord, NH 03301 =: 603.228.1122 hiturner.com
Change Order
PROJECT:
Jackson Mills Hydroelectric
TGC Upgrade Project
Nashua, NH
OWNER:
City of Nashua, NH
City Hall
229 Main Street, PO Box 2019
Nashua, NH 03061-2019
TO CONTRACTOR:
Mavel America, Inc.
121 Mount Vernon Street
Boston, MA 02108
Change Order No: 2
Date: August 6, 2021
Architect’s Project No: 5010
Contract for: Supply of Equipment
Contract Dated: July 8, 2020
Summary of Changes:
The supplier of the turbine/generator equipment (Mavel) shall store
all equipment at his factory, or a site nearby and postpone delivery
to the project site from August 14, 2021 to September 15, 2022.
Mavel’s supplier of the electrical control equipment (Eaton) shall
store all the electrical equipment at his factory, or a site nearby
and postpone delivery to the project site from September 15, 2021
to November 1, 2022. The combined cost of storage for the Mavel
and Eaton Equipment is $60,500.
The Contract is changed as follows: The dollar amount has increased and time for delivery is extended.
Not valid until signed by the Owner, Architect and Contractor
The original Contract Sum was $1,271,700
Net change by previously Authorized Change Orders $5,800.00 (Change Order No. 1)
The Contract Sum prior to this Change order was $1,277,500
The Contract Sum will be increased by this Change Order No. 2 in the amount of $60,500
Change Order #2.docx 5010
ARCHITECTS = ENGINEERS = BUILDING SCIENTISTS
©Copyright 2021 un
1 of2