104
Winchester Soccer Club Yee, VESRA waster oon
Winchester, MA <EL ENGINEERING, LLC
Phase II: Newly Constructed Steel Building
Phase Il consists of a 90,000 square foot indoor athletic stadium, the facility has overhanging mezzanines for
spectator viewing, cross fit exercise areas, locker rooms, showers, administrative offices, kitchen, dining area,
restrooms, and much more. The steel building has been erected and the interior finishes are scheduled to be
completed this year. Phase II also includes a bituminous concrete parking lot with improved drainage structures,
emergency access ways, utilities, seat walls and plantings.
Construction Progress Photo Construction Progress Photo