General Overview and Timetable
Activities
Timeline
10/03
to
10/09
10/10
to
10/16
10/17
to
10/23
10/24
to
10/30
10/31
to
11/06
11/07
to
11/13
11/14
to
11/20
11/21
to
11/27
11/28
to
12/04
12/05
to
12/11
12/12
to
12/18
PROJECT KICKOFF
Initial Meeting
Obtain Detailed Goals and Objectives
Establish Project Schedule
Establish Communication Roles
EXISTING CONDITIONS
Obtain GIS Data and Import to Civil 3D
Obtain LiDAR Data and Import to Civil 3D
Conduct Environmental Research
Obtain and Analyze Record Plans
Conduct Field Investigation
Conduct Geotechnical Exploration
Prepare Comprehensive Report
Prepare Existing Conditions Plan(s)
CONCEPTUAL OPTION DEVELOPME
Conduct Programming Meeting
Prepare Schematic Design Alternatives (3)
Prepare Cost Estimates for Each Alt.
Provide Summary of
Advantages/Disadvantages
Provide Permitting Considerations
Discuss Construction Considerations
Presentation Meeting
PREFERRED OPTION
Facilitate the Design of Preferred Option
Update the Cost Estimate
Prepare Phasing Options
Presentation Meeting
Refine design and cost further as needed
PROJET MEMORANDUM
Detailed Report
2D Color Rendering
3D Color Rendering
Deliver all documents Electronically
to City of Nashua
** The schedule may be modified as desired by the City of Nashua to provide faster completion by up to four
weeks.