Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 1/15/2020 - P141

Finance Committee - Agenda - 1/15/2020 - P141

By dnadmin on Mon, 11/07/2022 - 13:34
Document Date
Fri, 01/10/2020 - 11:24
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 01/15/2020 - 00:00
Page Number
141
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__011520…

EXHIBIT 3

SANBORN |

| H E AD 20 Foundry Street
Building Trust. Engineering Success. Concord, NH 03301
Mr. Jeff Lafleur November 12, 2019
Superintendent File No. 3066.18
Nashua Division of Public Works, Solid Waste Department
840 West Hollis Street Sent via email

Nashua, NH 03062

Re: Change Order Request
Construction Quality Assurance Services - Phase III
City of Nashua Four Hills Landfill
Nashua, New Hampshire

Dear Jeff:

Sanborn, Head & Associates, Inc. (Sanborn Head} appreciates the opportunity to be of
continued service to the City of Nashua (City). As we recently discussed, based on the
additional requirements imparted by the New Hampshire Department of Environmental
Services (NHDES) on the Phase III construction project and the associated construction
delays, we will exceed the approved budget for the Phase III Construction Quality Assurance
Services project. This letter presents our request for a change to our budget.

Background

Sanborn Head's original scope of services, described in our proposal dated February 18,
2019, included the following three (3) tasks:

a CQA Services;
m Construction Meetings/Documentation; and
a CQA Report.

However, during construction our scope evolved to include components that were not
anticipated at the time the existing budget was established. In addition, the total length of
the project was increased due to construction and permitting delays. Our original proposal
assumed that construction would take approximately 16 weeks, and as of the date of this
letter, the Phase III construction project is currently in its 26% week of construction. The
additional time and requests for services require a change to our approved budget.

Additional Services Already Provided

Since submitting the February 2019 proposal, several requests were made that were outside
our Construction Quality Assurance Services agreement. Below is a list of the major
differences that were not reflected in our proposal:

a Preparing narratives, figures, and tables associated with the Groundwater
Demonstration required by Condition 6 of the Phase III] permit, dated December 5, 2018;

SANBORN, HEAD & ASSOCIATES, INC. www.sanbornhead.com