Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$5,525,525.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: January 1, 2020
Ready for final payment: February 10, 2020
Net changes from previous Change Orders
$175,000.00
Net change from previous Change Orders
NONE
Contract Price prior to this Change Order
$5,700,525.00
Contract Times prior to this Change Order
Substantial completion: January 1, 2020
Ready for final payment: February 10, 2020
Net Increase (deerease} of this Change Order
$191,271.44
Net Increase (deerease)} of this Change Order
NONE
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$5,891,796.44 Substantial completion: January 1, 2020
Ready for final payment: February 10, 2020
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Representative Contractor Mayor James W. Donchess
(Authorized Signature) (Authorized Signature) Owner
(Authorized Signature)
Date: Date: Date:
Change Order #2 2 of 2
Phase II Landfill Expansion