c. Planning level capital cost estimate as well as estimates of impacts on
operating costs.
2. Summarize implementation plan recommendations and hold a workshop with
City staff to review and discuss. Workshop results to be included in Draft Report
(Task L).
K. Report
1. Generate a Draft Report summarizing the analysis, findings and recommendations
of facility planning efforts.
2. Meet with City staff, and if desired NHDES to discuss report and to review
comments.
3. Finalize the report and present to City staff.
L. CWSRF Assistance
1. Assist the City in preparing Clean Water State Revolving Fund Loan applications
for planning principal forgiveness and asset management principal forgiveness.
ENGINEER assumes that key City staff (i.e. WWTF Operations Manager; WWTF operational
staff, and City Planner as needed) will be available for the meetings/workshops identified above,
and will provide Wright-Pierce with necessary information including any available flow studies,
reports, plans, mapping, data, master plans, GIS files, and feedback/decisions, etc.
12/10/19 9 Wright-Pierce