December 10, 2019
Page 10
Item | SD | DD | cb | Bid | CA
HKT Architects Inc.
Principal 104 60 64 8 60
Sr. Designer 274 384 624 80 2248
Total $ $70,690 $78,060 $118,640 $15,160 $385,620
Reimb. Exp. Travel, Plotting, Delivery and Reprographics = $8,415
AKF Code Specialists
Total $ $8,500 [| $4,000 | $4,000 | $0 | $1,000
Reimb. Exp.
Kalin Specifications
Principal 6.7 33.33 26.67 0 0
Total $ $1000 $5,000 $4,000 $0 $0
Reimb. Exp. $0
Hoyle Tanner and Associates Inc.: Civil
PM Ill 24 8 8 8 16
Sr Eng Il 52 42 40 16 43
Eng | 28 68 85 8 8
PA Il 1 0 18 1 0
Total $ $14,235 $13,490 $16,490 $4,503 $9,587
Reimb. Exp. Travel, Plotting, Delivery and Reprographics = $796.11
Hoyle Tanner and Associates Inc.: Structural
Principal Eng 3 0 2 2 0
PM | 24 7 32 12 18
Sr Eng] 0 16 28 0 0
Eng II] 2 0 7 0 17
Eng Il 24 66 181 12 88
Eng | 10 3 18 6 0
CADD Tech It 0 8 80 0 0
PAI 2 0 2 4 12
Total $ $8,100 $11,095 $38,459 $4,358 $15,017
Reimb. Exp. Travel, Plotting, Delivery and Reprographics = $600
WVA Engineering Associates, PA
Project Mar. 10 12 14 5 36
Engineer 62 27 25 20 60
Designer 22 76 116 0 0
WP 16 13 9.5 5 23.5
Total $ $12,114 $12,897 $16,236 $3,510 $14,319
Reimb. Exp Included
lronwood Landscape Architecture
Principal 27 6 17 2 26
Larch Des 49 28 30 13 72
CADD/GIS 24 26 38 0 0
Admin 0 0 4 0 8
Total $ $8,575 $4,600 $6,900 $1,325 $9,380
Reimb. Exp. Travel, Plotting and Reprographics = $850
Sub-Total Per | $124,589 $131,351 $206,846 $29,205 $440,530
Phase with
reimbursables
Total Base $938,522
including
Reimbursables
Supplemental $ 58,682
Services
Pa
architescis inc.