and vegetation (including prime specimens and invasive species) will be
identified in the survey. No additional survey or wetland flagging is
included in this proposal.
Services of a Geotechnical Engineer are by others.
Investigative Services for Haz-Mat are by others.
No work by a professional cost estimator are included in this fee.
This project will endeavor to incorporate sustainable design principles if
the budget allows, but will not seek Certification under the U.S. Green
Building Council LEED Certification program. In addition, design of a Net
Zero energy performing building is excluded.
Additional impact studies, such as a traffic study, are not included in this
proposal. HTA will review work by City expert.
Energy Modeling is not included at this time because we assume that the
new building design will demonstrate energy code compliance using the
prescriptive path.
Material testing services during construction to be performed by others
(e.g. concrete testing, soil compaction testing, etc.).
Special Inspection Services for structural steel framing system, including
open-web steel joists and joist girders of the floor and/or roof systems, to
be performed by others.
Special Inspection Services, other than those identified under Construction
Administration, to be performed by others.
All fees assume the project construction documents will be prepared as a
single bid package.
The State of New Hampshire has adopted the 2015 ICC International
Codes effective September 15, 2019. The design team will review the
proposed design based on the 2015 codes. If a different version of the
code is adopted during design and revisions become necessary to design
work that is already completed, additional services may be required.
Offsite utility upgrades are not included in this proposal.
No NHDES permitting is included with the exception of the Sewer
Discharge.
Anew access drive entrance from West Hollis Street will be designed as
shown in City sketch.
Alteration to the existing recycling center area will not be included.
. Environmental, municipal or other permitting beyond what is in the above
scope is not included in this proposal.
Soil conditions at the site are assumed to be adequate for use of a shallow
cast-in-place spread footing foundation to support the praposed building.
Should it be determined that another solution is necessary, such as deep
foundations (i.e. pile-supported) or ground improvement, a contract
modification will be necessary to incorporate additional engineering scope
and fee.
Equipment cuts of all owner or vendor furnished equipment requiring
mechanical or electrical service will be provided to design team.
Sprinkler flow testing is excluded.
Fire protection hydraulic design with piping and head layout is excluded.
Mechanical design for the fire protection system will include sprinkler
entrance and main layout, along with a performance specification for final
hydraulic design by sprinkler subcontractor.
Data, telephone headend and security system hardware selections by
owner. Technology equipment procurement is not included.