Schedule of Values
LFG Header Replacement
(Add on to 2019 Landfill Gas System Expansion)
Four Hills Landfill
Nashua, New Hampshire
Item Description Quantity Bid Unit Cost Extended
No. P (w/ units) ($/units) Prices ($)
Connect to Existing 12"9 Header 1 | Ls | $2,000.00} Ls $2,000.00
Furnish & Install Landfill Gas Conveyance Pipe -
a. 6" Solid SDR 17 HDPE Pipe 720 | LE $70.00| LF $50,400.00
b. 12" Solid SDR 17 HDPE Pipe 620 | LF $87.00 | LF $53,940.00
3 |Furnish & Install Isolation Valve (12") 1 LS | $5,000.00} LS $5,000.00
Reconnect Wellhead Assemblies 28 EA $850.00] EA $23,800.00
Total) $135,140.00
Note:
1. All pipe lengths in the table above are plan view lengths (2D) and do not account for slope.