Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$323,470
CHANGE IN CONTRACT TIMES:
Original Contract Times
Final completion: December 18, 2019
Ready for final payment: January 17, 2020
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
None
Contract Price prior to this Change Order
$323,470
Contract Times prior to this Change Order
Final completion: December 18, 2019
Ready for final payment: January 17, 2020
Net Increasefdecrease} of this Change Order
$135,140
Net Increase (deerease} of this Change Order
Final completion: 135 calendar days
Ready for final payment: 30 calendar days
Contract Price with all approved Change
Orders
Contract Times with all approved Change Orders
Final completion: May 1, 2020
$458,610 Ready for final payment: May 31, 2020
RECOMMENDED: ACCEPTED: APPROVED:
Byo By: By
Sanborn Head & Associates SCS Field Services Mayor Jim Donchess
Engineer Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature}
Date: Date: Date:
Change Order # 1
IFB0593-080919
2 of 2
2019 Landfill Gas Collection and Control System Expansion