61
TITLE
Scope:The original estimate for the pipe support plan prior to the change required in PCO #3.
{LABOR
CATEGORY HRS RATE/HR PREMIUM SUBTOTAL LINE TOTAL TOTAL
SUBTOTAL $ 2,232.40
2-MATERIALS
DESCRIPTION QTy UNIT UNIT COST SUBTOTAL
Estimated
Clevice Hangers & Anchor Rods 41 $ 2,000.00] $ 2,000.00} $ 2,000.00
Dumpster / Disposai $ 750.00 | $ 750,00 | $ -
SUBTOTAL $ 2,000.00
SUBTOTAL 1 & 2 $4,232.40
Consider ($4,232.40) as a deduct in this overall PCO #3.