Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/5/2020 - P43

Finance Committee - Agenda - 2/5/2020 - P43

By dnadmin on Mon, 11/07/2022 - 13:33
Document Date
Fri, 01/31/2020 - 12:43
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/05/2020 - 00:00
Page Number
43
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__020520…

the notice, assign to the City of Nashua any orders or subcontracts specified in
the notice, and revoke agreements specified in the notice.

4. Not resume work after the effective date of a notice of suspension until receipt
ofa written notice from the City of Nashua to resume performance.

In the event of a termination, abandonment, or suspension at will, Independent Contractor
shall receive all amounts due and not previously paid to Independent Contractor for work
satisfactorily completed in accordance with the contract prior to the date of the notice and
compensation for work thereafter completed as specified in the notice. No amount shall
be allowed or paid for anticipated profit on unperformed services or other unperformed
work.

B. TERMINATION FOR CAUSE This agreement may be terminated by the City of Nashua
on 10 calendar day’s written notice to Independent Contractor in the event of a failure by
Independent Contractor to adhere to any or all the terms and conditions of the contract or
for failure to satisfactorily, in the sole opinion of the City of Nashua, to complete or make
sufficient progress on the work in a timely and professional manner. Independent
Contractor shall be given an opportunity for consultation with the City of Nashua prior to
the effective date of the termination. Independent Contractor may terminate the contract
on 10 calendar days written notice if, through no fault of Independent Contractor, the
City of Nashua fails to pay Independent Contractor for 45 days after the date of approval
by the City of Nashua of any Application for Payment.

Upon receipt of notice of termination for cause, Independent Contractor shall:

1. Immediately discontinue work on the date and to the extent specified in the
notice,

2. Provide the City of Nashua with a list of all unperformed services.

3. Place no further orders or sub-contracts for materials, services, or facilities,
other than as may be necessary or required for completion of such portion of
work under the contract that is not terminated.

4, Immediately make every reasonable effort to obtain cancellation upon terms
satisfactory to the City of Nashua of all orders or sub contracts to the extent they
relate to the performance of work terminated, abandoned, or suspended under
the notice, assign to the City of Nashua any orders or sub contracts specified in
the notice, and revoke agreements specified in the notice.

5. Not resume work after the effective date of a notice of termination unless and
until receipt of a written notice from the City of Nashua to resume performance.

In the event of a termination for cause, Independent Contractor shall receive all amounts
due and not previously paid to Independent Contractor for work satisfactorily completed
in accordance with the contract prior to the date of the notice, less all previous payments.
No amount shall be allowed or paid for anticipated profit on unperformed services or
other unperformed work. Any such payment may be adjusted to the extent of any
additional costs occasioned to the City of Nashua by reasons of Independent Contractor's
failure. Independent Contractor shall not be relieved of liability to the City of Nashua for
damages sustained from the failure, and the City of Nashua may withhold any payment to
the Independent Contractor until such time as the exact amount of damages due to the
City of Nashua is determined. All claims for payment by the Independent Contractor

GC 5 of 11