City of Nashua, Public Works Division
Board of Public Works Meeting Date: January 30, 2020
Nicholas Caggiano Superintendent
Parks and Recreation Department
Crown Hill Pool House
To approve a contract with Forcier Contracting & Building Services Inc of Nashua, NH
for the building repairs at the Crown Hill Pool bathhouse in the amount of $34,200.
Funding will be through Department: Department 177 Parks and Recreation; Fund:
Capital; Activity: Crown Hill Pool Building Repairs.
This project will replace the roof, 4 exterior metal doors with frames, the exterior siding
new counters and sinks. There is a one year warranty on workmanship and
manufactures warranty on each item. This work is to be completed by May of 2020.
The project was advertised on August 22, 2019. A pre-bid meeting was held on
September 3, 2019. Three contractors submitted qualified bids on October 18, 2019,
The bids are as follows:
Firm Bid
Fourcier Contracting & Building Services $34,200
Solid Roots Construction $34,825
Mark Carrier Construction, Inc $69,433
The bids were reviewed and Forcier Contracting and Building Services is the
recommended qualified, low bidder. The recommendation of the Superintendent is to
award the contract to Forcier Contracting and Building Services. This motion was held
at the November meeting until such time that the contractor and the city resolved the
parking issue at Artillery Lane. The issue has been resolved attached is the agreement
between the contractor and the city regarding this issue.