Finance Committee - 02/05/2020 Page 12
Mr. Caggiano
They are, within the contract, they are responsible. So occasionally they'll tip one over, gross but not bad. We
have had them burned before and they are insured, and if they get vandalized, that’s on the contractor.
Alderwoman Lu
Just two questions. How often, what is the billing cycle, is that a month?
Mr. Caggiano
A month.
Alderwoman Lu
OK and only have three ADA’s so are there some places where we don’t have an ADA there?
Mr. Caggiano
We have ADA’s at Roby Park because we have an ADA playground there. We have one at Legacy
Playground because that’s an ADA playground and | want to say, catch me on this one, | don’t have the sheet.
| want to say the other one is down at Whipple Street at the entrance to Mine Falls Park.
Alderwoman Lu
| just thought that we’d need one at every spot that we have to, but | guess that is not the requirement.
Mr. Caggiano
No and the cost is pretty significant to upgrade that.
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: Energy Recovery Upgrades — Construction Services — Change Order 4 (Value: $49,167)
Department: 169 Wastewater; Fund: Wastewater
MOTION BY ALDERMAN HARRIOTT-GATHRIGHT TO ACCEPT, PLACE ON FILE, AND AUTHORIZE
CHANGE ORDER #4 FOR ENERGY RECOVERY UPGRADES — CONSTRUCTION SERVICES - IN THE
AMOUNT OF $49,167 TO METHUEN CONSTRUCTION. FUNDS ARE AVAILABLE IN DEPARTMENT 169
WASTEWATER; FUND: WASTEWATER
ON THE QUESTION
Mayor Donchess
Mr. Caggiano?
Mr. Caggiano
I'll be speaking for my co-workers, they couldn’t make it tonight on these next two items. David is looking for a
Change Order #4 for an amount not to exceed $49,168.26. The basic need is to modify the generator pads
and re-do the ceiling pipes support structure.