Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$323,470
CHANGE IN CONTRACT TIMES:
Original Contract Times
Final completion: December 18, 2019
Ready for final payment: January 17, 2020
Net changes from previous Change Orders
$135,140
Net change from previous Change Orders
Final completion: May 1, 2020
Ready for final payment: May 31, 2020
Contract Price prior to this Change Order
$458,610
Contract Times prior to this Change Order
Final completion: December 18, 2019
Ready for final payment: January 17, 2020
Net Increase-deerease} of this Change Order
$287,565
Net Increase (decrease} of this Change Order
Final completion: June 1, 2020
Ready for final payment: June 30, 2020
Contract Price with all approved Change
Orders
Contract Times with all approved Change Orders
Final completion: June 1, 2020
$746,175 Ready for final payment: June 30, 2020
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
Sanborn Head & Associates SCS Field Services Mayor Jim Donchess
Engineer Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 2 2 of 2
IFB0593-080919
2019 Landfill Gas Collection and Control System Expansion