DESMAN
Page 2 of 20
2- CURRENT CONDI
2E
2F
2G
Zoning (Parking
Requirements)
Assessment
Existing Conditions
Assessment
First Public Forum
Nashu
Engineering, Planning,
Landscape Architecture
a sas bot sa
'
NEW HAMPSRIRE'S GATE CITY 4 MILONE & MACBROOM
Review how the City manages parking demand associated with 1) The Consultant Team will review the existing parking requirements impacting the
new development and/or change of use. Analysis to include
assessment of feasbility of allowing overnight parking and
practical application of in lieu fees including proposed
subsidized rate.
Consolidate work-to-date and review with Project Team
Outreach to general public to introduce engagement and
solicit input on existing conditions. This the first of three
forums for the general public, this will be oriented towards
drawing out input from the community about what is or is not
working within the existing parking system.
provision of parking in downtown including but not limited to: Parking requirements
per zoning; Acceptable waivers to these requirements; Alternates to existing waivers.
2) Analysis will benchmark existing requirements relative to comparable/aspirational
communities and industry best practices.
1) This would be 2nd meeting of Project Team. 2) Meeting would be to go through PPT
developed to summarize work to date. 3) Meeting would be followed with draft
deliverable for review
1) Meetings to be scheduled and arranged by the City. 2) First meeting will be "town
hall style" with an information presentation at the outset followed by an open question-
and-answer and comment session. 3) Consulting team will provide not more than five
(5) large scale maps illustrating existing conditions 4) Consulting team will record and
present meeting summary to the City within one (1) week after each set of meetings.
Confidential
2/26/2020