Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 4/15/2020 - P261

Finance Committee - Agenda - 4/15/2020 - P261

By dnadmin on Mon, 11/07/2022 - 13:32
Document Date
Fri, 04/10/2020 - 14:58
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 04/15/2020 - 00:00
Page Number
261
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__041520…

Part 3_City of Nashua, NH

Jackson Mills HPP

Ez SITE EQUIPMENT REQUIREMENTS

ix. Securing of external services and works procured
by the Purchaser (weld tests, certificates, painting,
consumables etc.) in requested time and quality.

x. Availability and readiness of energy, water,
cleaning means in requested quantity and quality
according to requirements of installation.

xi. Realization of installation time limits and time
schedule of installation.

xii. Taking over of Equipment readiness and/or

interface from other Suppliers.

inspection and surveillance

xiii. Negotiation with

authorities.

At least 30 days prior to commencement of the Technical
Advice, the Purchaser will inform the Supplier in writing of
the name of authorized Purchaser's Representative.

The Purchaser shall provide within required time and free of
charge the following:

a.

b.

Electric power, as requested by the Supplier.

Other utilities, resources, such as water, pressure air as
needed for installation.

All technical gases, such as oxygen, gas, for assembly
and installation, including safe storage.
Cranes with requested capacity for handling with
Equipment at storage and Project Site.

Vehicles or any other means necessary for shifting /
transfer / moving any Equipment at Project Site during
installation, if necessary (trucks, mobile cranes, hoisting
plattform, forklift etc.) including qualified and experienced
operators/drivers authorized for operation of such means.

Hoisting and rigging means (hydraulic jacks, tackles,
ropes, chains, straps, yokes).

. Clearance of at least of 50m’ in vicinity of the Project Site.

Covered storage / warehouse secured properly against
damage and theft of stored material and Equipment. All
electrical equipment shall be stored in an atmospherically
controlled environment.

Access roads, footways, protection handrails, foot-bridges,
ladders, stairs etc. for safe placement of Equipment and
safe motion in the power plant.

Lighting of the locality and securing of a minimum
temperature of +5°C at the place of assembly/installation.

Tools and equipment necessary for assembly and
installation as per specification of the Supplier.

Gauges, meters, calipers and other measuring means
necessary for assembly/installation and having respective
valid calibration protocols/certificates.

. Expendable supplies according to specification of the

Supplier.

Complete equipment and accessories for welding.
Equipment and qualified staff having respective
authorization for conducting and evaluation of non-

destructive tests.

Complete equipment for performance of surface protection
of Equipment and/or paint repairs.

Statically secured space for assembly/installation serviced
by means of the crane.

Secured spaces for storage of supplied Equipment from
the date of delivery to the Project Site up to installation,
storage and placement of hazardous material in
compliance with valid rules and regulations.

Lockable protected room for storage and placement of
special tools, instruments and other sensitive materials for
the time period requested by the Technical Advisor.

Access to telephone and fax set, internet access, PC with
E-mail; printer to PC at the Project Site.

One lockable office/room with sufficient area for Technical
Advisors available for the period of their whole stay at
Project Site, which shall be equipped at least by:

i. table and chairs (one for four persons)

ii. lockable cabinet for documentation

iii. A/C and/or heater, as needed.

iv. clothes-rack

v. atleast 2 electrical sockets 120V

vi. sufficient lighting

vii. door keys

9. EMERGENCIES AND UNUSUAL EVENTS

a.

In case of any serious illness, epidemic, infection in the
area near the Project Site or accommodation, which could
endanger the health of the Technical Advisor, the
Purchaser is obliged to inform the Technical Advisor and
take immediate measures for his protection. In such case,
the Technical Advisor may request a change in the place
of accommodation. Or, if it is not possible to protect
effectively the Technical Advisor’s health, he may then
interrupt his stay and leave the Project Site.

Page Image
Finance Committee - Agenda - 4/15/2020 - P261

Footer menu

  • Contact