Jackson Mills HPP GENERAL CONDITIONS (PART 1)
City of Nashua Page 8 of 20
7.4.2. If, in the opinion of the Purchaser, the critical path of the Project Schedule will be adversely
affected by delays in completing the Equipment, the Purchaser may request the Supplier to
employ additional labour and equipment or work overtime or employ any other necessary
procedures, at no cost to the Purchaser, to bring the supply of the Equipment back on the
Contract Work Schedule.
8. Suspension of Work
8.1.
8.2.
8.3.
8.4.
8.5.
8.6.
The Supplier has the right to suspend the Work as per Article 8.5 of the Agreement
The Purchaser may, for its convenience or for just and sufficient cause, suspend the Work in whole or in
part at any time by written notice to the Supplier stating the extent and effective date of such
suspension; whereupon the Supplier shall:
8.2.1. except as necessary for the care and preservation of portions of the Work and upon notice of
same to the Purchaser, suspend the Work to the extent specified;
8.2.2. place no further orders or subcontracts relating thereto;
8.2.3. take any action on such orders and subcontracts as may reasonably be required to either obtain
suspension terms satisfactory to the Purchaser or as the Purchaser may direct; and
8.2.4. continue to perform any and all portions of the Work that have not been suspended.
The Purchaser may, at any time, authorize resumption of any suspended work or any part thereof, by
giving the Supplier thirty (30) days written notice specifying the part of the suspended work to be
resumed and the effective date of such resumption. The Supplier shall resume the suspended work on
the date and to the extent specified in the notice of resumption.
The Supplier will be allowed an extension of the Contract Times directly attributable to any delay
resulting from an action taken under Article-3-5; 8.1, 8.2, or 8.3 er 20-5 hereof. The extension of the
Contract Times shall be no less than the period of the suspension, unless otherwise agreed by the
Parties, and documented by means of a written Change Order.
The Supplier will be entitled to an increase in the Contract Price for added expenses directly incurred as
a result of such delays suspensions, unless such delays-suspensions are due to the acts or omissions of
the Supplier. The increase in the Contract Price shall be documented by means of a written Change
Order.
In the event that such suspension or the total of all such suspensions described in Article 8.2 exceeds
more than sixty (60) days, then the Supplier shall provide the Purchaser with the list of all costs incurred
by the Supplier. Upon agreement between the Purchaser and Supplier as to such costs, the Purchaser
shall pay such costs to the Supplier within fourteen (14) days from receipt of the Supplier’s invoice,
unless such suspension is due to the acts or omissions of the Supplier or any Sub-supplier. The Supplier
will continue to submit costs every thirty (30) days as noted above until the work is resumed and the
Purchaser will continue to pay such costs to Supplier.