Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$2,825,135.00
CHANGE IN CONTRACT TIMES;
Original Contract Times
Substantial completion: October 30, 2019
Ready for final payment:
November 29, 2019
Net changes from previous Change Orders
30
Net change from previous Change Orders
36 days
Contract Price prior to this Change Order
$2,825,135.00
Contract Times prior to this Change Order
Substantial completion: November 29, 2019
Ready for final payment:
December 29, 2019
Net Increase (decrease} of this Change Order
$1,560,000.00
Net Increase (deerease} of this Change Order
365 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$4,325,135.00 Substantial completion: November 29, 2026
Ready for final payment: December 29, 2020
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature}
Date: Date: Date:
Change Order # 2 2of2
IFBO1087-021219
2019 CIPP Lining Project