CHANGE ORDER
No. 1
PROJECT: _ Chamber Renovations
DATE OF ISSUANCE: 02.18.2020 EFFECTIVE DATE: 02.18.2020
OWNER: City of Nashua
OWNER's Contract No. 1
CONTRACTOR: DL King ENGINEER: N/A
You are directed to make the following changes in the Contract Documents.
Description: Hygienist Asbestos Testing, Hazmat Testing, Supply/Install Flooring, Drawer to Desks and Strip
Lighting/Desks.
Reason for Change Order: Increased scope of work to include flooring upgrade and improved desk design.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion:03.20.2020
$134,900 Ready fer final payment: At Completion
days or dates
Net changes from previous Change Orders Net change from previous Change Orders
No. Ota No. 1 No. ta No. :
$12,358.06
days
Contract Price prior to this Change Order Contract Times prior to this Change Order
Substantial Completion: 03.20.2020
$134,900 Ready for final payment: At Completion
days or dates
Net Increase (decrease) of this Change Order | Net Increase (decrease) of this Change Order
$12,358.06
days
Contract Price with all approved Change Contract Times with all approved Change
Orders Orders
Substantial Completion: 03.20.2020
$147,258.06 Ready for final payment: At Completion
days or dates
RECOMMENDED: APPROVED: ACCEPTED:
By: By: By:
Engineer (Authorized Signature} Owner (Authorized Signature) Contractor (Authorized Signature)
Date: Date: Date:
CO-1 of 2