Summary
CHANGE EN CONTRACT PRICE:
Original Contract Price
$48,600.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: Oct 15, 2019
Ready for fmal payment: Oct 31, 2019
Net changes from previous Change Orders
$22,800.60
Net change from previous Change Orders
None
Contract Price prior to this Change Order
$71,400.00
Contract Times prior to this Change Order
Substantial completion: Oct 15, 2019
Ready for final payment: Oct 31, 2019
Net Increase (decrease) of this Change Order
$94,400.00
Net Increase (decrease) of this Change Order
365 Days
Contract Price with all approved Change Orders
Coniract Times with all approved Change Orders
$165,880.00 Substantial completion: Oct 15, 2620
Ready for final payment: Oct 31, 2020
RECOMMENDED: ACCEPTED: APPROVED:
By: Mark Saunders By: By:
DPW merac Mayor Jim Donchess
Engineer Owner
{Authorized Signature) (Authorized Signature} (Authorized Signature)
Date: 03-23-2020 Date: Uo 2e 20 Date:
Change Order #2 2019 Asphalt Testing 2 of 2