PCO #016
Methuen Construction Co., Inc. Project: 181012 - Nashua Energy Recovery Upgrade
144 Main Street - PO Box 980 2 Sawmill Rd.
Plaistow, New Hampshire 03865 Nashua, New Hampshire 03060
Phone: (603) 328-2222
Prime Contract Potential Change Order #016: JWP Install
TO: City of Nashua FROM: Methuen Construction Co., Inc.
229 Main Street 144 Main Street PO Box 980
Nashua New Hampshire, 03060 Plaistow New Hampshire, 03865
PCO NUMBER/REVISION: 016/0 CONTRACT: IFB0501-090678 NASHUA PO #146861 -
Nashua Energy Recovery Upgrade
REQUEST RECEIVED FROM: ~ GREATED BY: Denise Freudenberg (Methuen Construction
Co., Ine.}
STATUS: Pending - In Review CREATED DATE: 3/5 /2020
‘REFERENCE: st — DATESENT: 3/5/2020 —
FIELD CHANGE: No PRIMECONTRACT None —
CHANGE ORDER:
LOCATION:
SCHEDULE IMPACT: ACCOUNTING Amount Based
METHOD:
PAID IN FULL: No TOTAL AMOUNT: $2,246.76
Methuen Construction (MC}, hereby submits this PCO in accordance with the documentation referenced herein. It is expressly understood and agreed
that this proposal is valid for the time as specified within this document from the date of the PCO. The Proposal is based upon current day construction
costs and does not include escalation costs for any material items that are either volatile or market sensitive. This Proposal does not include overtime
acceleration or expediting costs. This proposal does not include the costs associated with out of sequence construction, interference, impact related
delays and disruptions, MC reserves its rights under the agreement to seek additional time, indirect and impact costs associated with the PCO, once the
impacts can be fully evaluated. This proposal is submitted based on the understanding that it is exempt from WBE/MBE participation requirements and
acceptance of this proposal waives the participation requirements associated with this additional work.
POTENTIAL CHANGE ORDER TITLE: JWP Install
CHANGE REASON: No Change Reason
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract ls Changed As Follows)
CE #039 - JWP Install
The 2 Jacket Water Pumps, tying into each of the generator engines were not shown on contract drawings. The scope of work to install these pumps
consisted of cutting unistrut to match the width of WHE 1 & 2. Two pieces of unistrut were cut at 3'2" to rest parailel fram each other across the tap of
each WHB frame. Upon cutting the unistrut to size, it was then anchored into the WHB frames. Each JWP were then bolted to the unistrut, and
supported by threaded rod anchored to the unistrut support system in the ceiling. This method of install was done on both frames, requiring 2 laborers
and 1.5 days worth of work.
ATTACHMENTS:
a Burden Rate
# | Cost Code Description Type Amount (43,00% Applies to Labor) Subtotal
i bo#-0002 ~~ | Labor Labor $ 1,339,44 $575.96 $4,915.40
Sick Time
Subtotal: | $1,339.44 | $575.96 34,915.46
GC Work Total Feo - Labor: 15.00% Applies to Labor. $ 287.31
Methuen Construction Co., Inc. page 1 of 2 Printed On: 3/6/ 2020 09 :55 AM