Finance Committee - Agenda - 5/6/2020 - P128

By dnadmin on Mon, 11/07/2022 - 13:31
Document Date
Fri, 05/01/2020 - 14:46
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/06/2020 - 00:00
Page Number
128
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__050620…

The table below summarizes the total value of the work.

Claimed Cost | Fair Market Value | AHowable Mark-up** | Total Value Assessment
of Work of Work scope
52,246.76 $2,900 (includes 15% on MC Work $2,552.00 to $3,828.00
materials & 10% on Subs (<$50k)
equipment)* 7-1/2% on Subs ($50-
100k)
5% on Subs (> 1001)

*Market Value Assessment=$2,320 to $3,480 (+/- 20%)
** This review assumes all labor performed by subcontractors. See below.

Detailed Review-Superintendent Labor Hours
The General Contractor did not claim any direct labor hours for his superintendent. The scope of
work was performed by laborers.

Detailed Review-General Contractor Markup
The General Contractor self-performed this task and did not apply markup.

Detailed Review-Schedule

Methuen did not make a claim for schedule adjustment and as such no review was conducted.

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None n/a n/a 0
Conclusion

Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question.

Waldron recommends approving $2,246.76 of the claim as noted above 0 days of schedule relief.

If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
148 or egustenhoven@waldron.com

Sincerely
Waldron Engineering & Construction, Inc.

Erich L Gustenhoven, P.E.