PROJECT NAME: Date: 9-Jan-20
Nashua Primary Tank Upgrades
PROJECT NO: 181016
PHASE
COST SUMMARY SHEET
PLC Processor Upgrade
A Nic Labor (Recap Sheet): $0.00
B WiC Materials, & Equipment (Recap Sheet): $0.00
c MC Fee (A x 15%) + (B x 15%): $0.00
DB Subtotal MIC Work (A+B+C): 75 -
E Total Subcontractors (Below): $2,725.50
F MC Mark-up on Subconiractor Work (5%, 7.5% or 16%): | $ 237.00
G Bond (1%} and General Liability (1%): $59.25
Total Proposal (D+E+F+G): $ 3,021.75
SUBCONTRACTOR SUMMARY
ubcontractor Description
El PLC Processor Upgrade 3
$
$
3
3
$
3
Total Subcontractors:
Amount
2,725.50
2,725.50
Page Image