Electrical Building Relocation
Scope: Original excavation to find unknown electrical duct bank. Re-Excavation for new location of building and New utility trench
locations, Core new hele and connect drainage to existing storm drain structure. Remove existing siairs (Reinstall of stairs is not
covered in this PCO). Install new grout between new electrical building and stair tower, Site work costs credits for this PCO include
removing all pavement requested in RFP 4 as well as all Contract pavement (not completed already} shown on contract drawing C-
4
SUBTOTAL $7,025.00
GC MARKUP (typically 10%) x (Subcontractor cost/1.15) $610.87
8-FEE
GC (15% X ttems 7165 + 15% X Items 28384 + 5%, 7.5% or 10% X Item 7} $1,356.14
8-SUBTOTAL $13,349.58
8-SUBTOTAL WITH CREDIT $5,153.79
BOND (1% X item8) $51.54
GENERAL LIABILITY (1% X Htem 8) $51.54
9-TOTAL (item & + Bond + General Liability) $5,256.86