eIndustral Doc #: PCO7
ER ICES
SET ee nemecinc Ref. Document:
PROJECT: Nashua Primary Tank , Date: 5-Mar-20
Upgrades
PROJECT NO: 181016
PHASE
COST SUMMARY SHEET
Electrical Building Relocation
A MC Labor (Recap Sheet): $4,282.70
B KIC Materials, & Equipment (Recap Sheet): $686.34
Cc MIC Fee (A x 15%) + (B x 15%): $745.27
D Subtotal MC Work (A+B+C): | $ 5,713.71
E Total Subcontractors (Below): $7,025.00
F MC Mark-up on Subcontractor Work (5%, 7.5% or 10%): | $ 610.87
G Bond (1%) and General Liability (1%): $103.08
H DEDUCTIONS- CB,DMH1,6" LPA, YARD HYDRANT, PW DEMO ($8,195.79)
Total Proposal (D+E+F+G): $ 5,256.86
SUBCONTRACTOR SUMMARY
Subcontractor Description Amount
ROADWAY EXCAVATES |PAVEMENT, EXCAVATIONS, & DUCT BANK $ 7,425.00
AHA] A oe io
E
Total Subcontractors: 7,025.00