Section IV: Health, Safety & Environment
Our price includes having all our personnel properly trained pursuant to all state and federally mandated
OSHA and EPA standards and they will have the necessary PPE and be fully trained and qualified within
their respective trades, on the specific equipment they are working with, and the present and potential
hazards associated with the industrial environment in which we are working in. Our price does not include
the exposure of our personnel, to others or the environment to any previously applied coatings that
contain any hazardous materials, including, but not limited to, lead, asbestos or cadmium containing
compounds. If the presence of hazardous materials is unknown, we suggest samples of the existing
coatings should be taken to ascertain and evaluate the levels, if any, of hazardous substances to insure
compliance to all local, state and federal EPA and OSHA regulations. Our price includes all of our fieid
personnel receiving a safety briefing at your location, provided by others to acquaint our staff with the
specific health, safety and environmental considerations at the site, if necessary. Our pricing includes the
proper handling and disposal of all waste materials we generate on the project in customer provided
dumpster.
Section V: Quality Contral and Assurance
This project will be assigned a NACE or SSPC Certified Coating Inspector for quality control purposes. Our
corporate Quality Control (QC) programs are administered on an ongoing basis by a NACE or SSPC Level 3
Certified Coating Inspector. A site-specific inspection plan will be written and presented to you for your
consideration and approval prior to the commencement of our scope of work at your written request.
Section Vi: Schedule
Our pricing is based upon one mobilization to the site and continuing to proceed with our work on a full-
time basis, in one mobilization, until project is completed. We anticipate the project taking 7 calendar days
(weather permitting) in order to be in compliance to coating cure times and overcoat times.
Section Vil: Clarifications and Requiremenis
4. Our standard work hours are Monday thru Friday, 8:00 AM to 4:30 PM but hours may be adjusted
at the discretion of contractor to start as early as 6:00 AM and/or finish at sundown.
JB Safety International, Inc. ¢ P.O. Box 476 @ Seguin, TX 78156 ¢ 281-857-7919 éjeff@jbsafetyintl.com
htip:/Avww.jbsafetyinil.com
Page [5