PROJECT NAME: Date: 23-Dec-19
Nashua Primary Tank Upgrades
PROJECT NO: 181016
PHASE
COST SUMMARY SHEET
Weirs Altachement
A iC Labor (Recap Sheet): $20,256.51
B Mc Materials, & Equipment (Recap Sheet): $6,590.20
Cc RIC Fee (A x 15%) + (B x 15%): $4,027.01
D Subtotal MC Work (A +B+4C): | $ 30,873.72
E Total Subcontractors (Below): $741,006.00
F MC Mark-up on Subcontractor Work (5%, 7.5% or 10%): | $ 956.52
G Bond (1%) and General Liability (1%): $716.12
H DEDUCT SOV FOR GT WEIRS DENIO (SEE ATTACHED) (37,024.01)
Total Proposal (D+E+F+G): § 36,522.35
SUBCONTRACTOR SUMMARY
Subcontractor Description Amount
JB Safety International Sandblast & paint weirs for 2 GT $ 711,000.00
A | tA tal oa fee |
E
Total Subcontractors: 11,006.00