CHANGE ORDER
No. 4
PROJECT: Primary Tank Upgrade Project DATE OF ISSUANCE: —_ 3/16/20
OWNER: City of Nashua, New Hampshire
229 Main Street
(Address) ) OWNER’S Purchase Order No.
CONTRACTOR: Methuen Construction OWNER’s Project No. IFB 0285-112918
CONTRACT FOR: _ Primary Tank Upgrade Project ENGINEER —Wright-Pierce
ENGINEER’s Project No. 13774
You are directed to make the following changes in the Contract Documents.
Description: See attached backup from Methuen Construction for various PCOs. Wrighi-Pierce and the
City waived the requirement for Methuen to provide additional breakdown for PCOs-05 and -07 but will
require Methuen to provide all subcontractor breakdowns for all future change orders.
Purpose of Change Order: Change in contract price for additional work and deductions from credited
work
Attachments: Methuen PCO NO. 05 Weirs and Baffles, Methuen PCO NO. 06 Balancing Change Order,
Methuen PCO NO. 07 Electrical Building Relocation, PCO NO. 08 PLC Processor Upgrade
CHANGE IN CONTRACT PRICE
Original Contract Price
$ _3,629,340.00
CHANGE IN CONTRACT TIME
Original Contract Time
Subs. Completion: 6/18/20 / Final: 8/17/20
(days or date}
Previous Change Orders
$ 28,462.09
Net change from previous Change Orders
Subs. Completion: 0 / Final: 0
(days)
Contract Price prior to this Change Order
$ _3,657,802.09
Contract Time prior to this Change Order
Subs. Completion: 6/18/20 / Final: 8/17/20
(days or date)
Net Increase (Decrease) of this Change Order
$ 46,335.68
Net Increase (decrease) this Change Order
Subs. Completion: 35 / Final: 35
{days)
Contract Price with all approved Change Orders
$ _3,704,137.77
Contract Time with all Change Orders
Subs. Completion: 7/23/20 / Final: 9/21/20
(days or date}
This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.
Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that
the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.
RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: By: Clecoph, tite, — By:
2 Owner "Contractor NHDES
4/15/2020 ANS [20
Date Date Date Date