5/15/2020
BA CY {Crushed Gravel $30,00 220 CY $6,600,00
&B SY {Temporary Bituminous Pavement Patch including 18" Crushed Gravel Base $35.00 435 sY $15,225.00
8c TON __|Hot Bituminous Pavement (Permanent Binder and Base Courses) $175.00 350 TON $61,250.00
8D LE |Sawed Bituminous Pavement $1.25 2600 LF $3,250.00
8E CY [Unclassified Excavation $27.50 220 cy $6,050.00
9B SY ___|4" Concrete Sidewalk Repair Including Crushed Gravel Base $86.50 20 SY $6,920.00
10A LF |Reset Granite Curb $25.00 70 LF $1,750.00
12 EA [Silt Sack $106.00 7 EA $700.00
[4 AtCost |Uniformed Police Officers $5,000.00 1 Ai Cost $5,000.00
1s {HR Flaggers $25,50 240 HR $6,120.00
19 |HR Night Work Ordered by City $175.00 P20 HR $21,000.00
TOTAL ESTIMATED COST FOR MAIN STREET (W. HOLLIS TO MULBERRY) $263,940.00
SUMMARY OF THIS CHANGE ORDER REQUEST:
WATER STREET
AMHERST STREET (VERNON TO BEACON)
MAIN STREET (W. HOLLIS TO MULBERRY)
TOTAL THIS CHANGE ORDER REQUEST
$ 532,705.00
3178,480.00
$263,940,00
$ 975,125.00