Summary
CHANGE EN CONTRACT PRICE:
Original Contract Price
$1,497,993.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 6, 2020
Ready for final payment: November 6, 2020
Net changes from previous Change Orders
30
Net change from previous Change Orders
6 days
Contract Price prior to this Change Order
$1,497,993.00
Contract Times prior to this Change Order
Substantial completion: October 6, 2020
Ready for final payment: November 6, 2020
Net Increase (deerease} of this Change Order
$975.125.00
Net Increase fdeerease} of this Change Order
210 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$2,473,118.00 Substantial completion: May 4, 2021
Ready for final payment: June 4, 2021
RECOMMENDED: ACCEPTED: APPROVED:
By: ‘ol | v_ By: By:
() Dpw Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature} (Authorized Signature)
Date: 05/26/2020 Date: Date:
2020 Sewer Renlacement Project 2of2 Change Order #1