20206 SIDEWALK PROGRAM
REPLACE SECTION 692 —- MOBILIZATION
Jtem 692 — Mobilization
A. SCOPE
This item shall consist of preparatory work and operations, including, but not limited
to, those necessary to the movement of personnel, equipment, supplies and incidentals
to the site of the work and for all other work and operations which must be performed
or for costs which must be incurred prior to beginning work on the various items. Also
included in this item is the breakdown and transport of all equipment, supplies and
material from the site (demobilization).
B. MATERIALS AND CONSTRUCTION
The Contractor shall furnish all materials, labor and equipment necessary for
mobilization in accordance with relevant provisions of the NHDOT Standard
Specifications for Road and Bridge Construction, latest edition as amended herein.
Cc MEASUREMENT AND PAYMENT
Mobilization will be measured as a lump sum unit. Payment for mobilization shall be
at the contract unit price, and shall include full compensation for material, equipment
and labor to complete this portion of the Bid Schedule. Payment will be made at
intervals for the prorated portion of the unit bid price for this item. Two payments at a
rate of 50% of the unit bid price will be made. The first payment shall be made after
complete mobilization to the project site and the second payment shail be made after
complete demobilization from the project site and only after all final punch list items
and clean-up work have been addressed. The total bid price for mobilization shall not
exceed five percent (5%) of the total of all bid items excluding this item.
Item 692 Mobilization (not to exceed 5% of Bid) Unit