2020 Sidewalk Program
responsibility to inspect all materials and devices for maintenance of traffic and correct
any deficiencies on a daily basis.
Regardless of action that may be taken or not taken by the Engineer, the
CONTRACTOR shall be solely responsible for the appropriateness, reflectivity and
condition of all materiais provided as well as placement and maintenance of traffic
contro! elements.
The CONTRACTOR shall submit a Traffic Control Plan prior to work on arterial
roadways. This Traffic Control Plan will describe how the CONTRACTOR proposes
to:
e Stage the work to maintain and control traffic during the demolition and
reconstruction of curb and sidewalks.
e Maintain access to all residences and businesses through the duration
of construction.
e Lane usage during various phases of work will be described. A minimum of
11- foot width shall be provided for all lanes open to traffic. Pedestrian traffic
around the work area shall be maintained at all times.
e A minimum of one lane in each direction shall be provided at all times.
Should the CONTRACTOR consider it necessary to reduce this requirement to
alternating one- way use, the constraints justifying such a restriction must be
explained fully. If approved at any location in this contract, the use of
alternating one-way traffic will be for a short duration only.
e The CONTRACTOR shall describe in the Traffic Control Plan minimum
conditions which will be provided at the end of working hours.
e Full lane use shall be maintained for weekend and holiday periods.
i V. QD RPLUS M RIAL
Neither debris nor surplus material shal! be deposited on private property or impede
pedestrian ways. Debris and surplus material shall be removed from the project area as
promptly as practical.
PROTECTION OF LANDSCAPING
CONTRACTOR shall take appropriate measures to protect trees, shrubs and other
jandscaping. Branches, limbs and roots shall not be cut except with permission of the
Engimeer. Where cutting is necessary, work shall be performed by qualified workers.
RESTORATION OF EXISTING PROPERTY
The CONTRACTOR shall be responsible for the preservation of all public and private
POW 6 of 7