Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/3/2020 - P258

Finance Committee - Agenda - 6/3/2020 - P258

By dnadmin on Mon, 11/07/2022 - 13:30
Document Date
Fri, 05/29/2020 - 15:04
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/03/2020 - 00:00
Page Number
258
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060320…

2020 Sidewalk Program

PROSECUTION OF WORK

This Prosecution of Work shall amend or supplement the Standard General Conditions of the

Construction Contract and other provisions of the Contract Documents as indicated below.

AH provisions which are not so amended or supplemented remain in full force and effect.

1.

DESCRIPTION OF WORK

This project involves the reconstruction of pedestrian sidewalks with new and reset
granite curbing on a portion of East Hollis Street from 242 Main Street (CVS Pharmacy)
to Harbor Avenue. The Contractor wili provide all labor, equipment, and material to
construct the improvements shown on the “2020 Sidewalk Program” plans.

The City reserves the right to remove sidewalk and ramp sections from the list, extend
or shorten limits, or revise the specified treatment.

The City may also add additional sidewalks and ramps to the contract work.

Should the net projection of the value of changes to the contract work exceed
the authorized amount, the Owner will present a contract amendment proposal
to the CONTRACTOR.

CITY OF NASHUA OVERSIGHT AND INSPECTION

The City is the Engineer and Owner for this project and will provide a project
representative to act as their agent overseeing the project. The CONTRACTOR must
provide full access to the project site at all times to City personnel and agents of the

City.

MILESTONES FOR SUBSTANTIAL COMPLETION
The entire length of all sidewalk and ramps shall be substantially complete by August 7,

2020.

WORK HOURS

Reference is made to Section 6.02 Labor; Working Hours of the General Conditions.

East Hollis Street work hours shall be 8:00 AM to 4:00 PM Monday through Friday of
each week if the CONTRACTOR maintains a minimum of one lane in each direction at
all times. Should the CONTRACTOR consider it necessary to reduce this requirement to
alternating one- way use, work shall be limited to 9:00 AM - 3:00 PM, Monday through
Friday of each week.