Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.
Prior to the start of construction, the Contractor shall submit a comprehensive schedule to the
Engineer for review and acceptance.
The schedule will identify the number of crews and completion dates for all critical elements of
work.
Detailed updates of the schedule shall be submitted to the Engineer for review and acceptance
on at least a weekly interval.
The Contractor shall not increase the number of crews assigned to the work as identified in the
schedule without providing at least one week advanced notice to the Engineer.
SUPERINTENDEN HE W.
Reference is made to General Conditions Section 6.01, Supervision and Superintendence,
Contractor shall provide appropriate onsite superintendence of all aspects of the work whether
performed by the Contractor or by subcontractors.
Qualified Superintendent(s) shall be assigned for all crews. The Contractor shall provide
contact information for all Superintendents.
PERATION WI KUP
The Contractor shall determine the schedule for trash pickup by contacting the City of
Nashua’s Solid Waste Department. The Contractor shall cooperate and make arrangements to
insure that trash pickup is not delayed or obstructed in any way. This may involve the
Contractor bringing trash barrels to the front or backside of the work area for pickup by the
Solid Waste Department and then returning the barrels back to each house.