6.10 TYaxes
A. CONTRACTOR shall pay all sales, consumer, use, and other similar taxes required to be paid by CONTRACTOR
in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance
of the Work
6.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas
1. CONTRACTOR shall confine construction equipment, the storage of materials and equipment, and the
operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably
encumber the Site and other areas with construction equipment or other materials or equipment. CONTRACTOR
shall assume full responsibility for any damage to any such land or area, or to the OWNER or occupant thereof, or
of any adjacent land or areas resulting from the performance of the Work.
2. Should any claim be made by any such OWNER or occupant because of the performance of the Work,
CONTRACTOR shall promptly settle with such other party by negotiation or otherwise resolve the claim by
arbitration or other dispute resolution proceeding or at law.
B. Removal of Debris During performance of the Work:
During the progress of the Work CONTRACTOR shall keep the Site and other areas free from accumulations of
waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Cleaning:
Prior to Substantial Completion of the Work CONTRACTOR shall clean the Site and make it ready for utilization
by OWNER. At the completion of the Work CONTRACTOR shall remove from the Site all tools, appliances,
construction equipment and machinery, and surplus materials and shall restore to original condition all property not
designated for alteration by the Contract Documents.
D, Loading Structures:
CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will endanger
the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures
that will endanger it.
E. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless
OWNER, ENGINEER, ENGINEER’s Consultant, and the officers, directors, partners, employees, agents, and other
consultants of each and any of them from and against all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration
or other dispute resolution costs) arising out of or relating to any claim or action, legal or equitable, brought by any
such OWNER or occupant against OWNER, ENGINEER, or any other party indemnified hereunder to the extent
caused by or based upon CONTRACTOR’s performance of the Work.
6.12 Record Documents
A. CONTRACTOR shall maintain in a safe place at the Site one record copy of all Drawings, Specifications, Addenda,
Written Amendments, Change Orders,
Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during
construction. These record documents together with all approved Samples and a counterpart of all approved Shop
Drawings will be available to ENGINEER for reference. Upon completion of the Work, these record documents,
Samples, and Shop Drawings will be delivered to ENGINEER for OWNER.