Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/3/2020 - P101

Finance Committee - Agenda - 6/3/2020 - P101

By dnadmin on Mon, 11/07/2022 - 13:29
Document Date
Fri, 05/29/2020 - 15:04
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/03/2020 - 00:00
Page Number
101
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060320…

CONTRACTOR does not make the request or does not provide the certificate before the expiration of the six-
month period, CONTRACTOR agrees that OWNER may order the CONTRACTOR to stop work, suspend the
contract, or terminate the contract.

H. To be deemed a responsive bid, the list of subcontractor form must be submitted even if no subcontractors
are required to be listed. Submittal is as follows:

1. Each bid submitted to any officer, department, board or commission for the construction of any public
work or improvement must include:

a. The name of each subcontractor who will provide labor or a portion of the work or improvement to
the CONTRACTOR for which he will be paid an amount exceeding 5 percent of the prime
CONTRACTOR’: total bid. Within 2 hours after the completion of the opening of the bids, the general
contractors who submitted the three lowest bids must submit a list of the name of each subcontractor
who will provide labor or a portion of the work or improvement to the CONTRACTOR for which he
will be paid an amount exceeding 1 percent of the prime CONTRACTOR’s total bid or $50,000,
whichever is greater, and the number of the license issued to the subcontractor. If a general
CONTRACTOR fails to submit such a lst within the required time, his bid shall be deemed not
responsive.

b. A description of the portion of the work or improvement which each subcontractor named in the bid
will complete.

2. The CONTRACTOR shall list in his bid the name of a subcontractor for each portion of the project that
will be completed by a subcontractor.

3. A CONTRACTOR whose bid is accepted shall not substitute any person for a subcontractor who is
named in the bid, unless:

a. The awarding authority objects to the subcontractor, requests in writing a change in the
subcontractor and pays any increase in costs resulting from the change; or

b. The substitution is approved by the awarding authority and:

(i) The subcontractor, after having a reasonable opportunity, fails or refuses to execute a written
contract with the CONTRACTOR which was offered to the subcontractor with the same terms that
all other subcontractors on the project were offered;

(ii) The named subconiractor files for bankruptcy or becomes insolvent; or

(iii) The named subcontractor fails or refuses to perform his subcontract within a reasonable time
or is unable to furnish a performance bond and payment bond.

I. If blasting or use of explosives is necessary for prosecution of Work, the CONTRACTOR shall provide the
ENGINEER with a blasting plan in compliance with OSHA, State, and local regulations, laws, ordinances, and
requirements. CONTRACTOR shall exercise the utmost care not to endanger life or property. CONTRACTOR shall
be responsible for all damage resulting from the use of explosives. CONTRACTOR shall notify each property
OWNER and utility company having structures or facilities in proximity to the site of the work of its intentions to use
explosives. Such notice shall be given sufficiently in advance to enable the utility companies to take such steps as they
may deem necessary to protect their property from injury.