Sunday, or any legal holiday without OWNER’s written consent (which will not be unreasonably withheld) given after
prior written notice to ENGINEER.
C. The following list of streets may not be opened or worked in between the hours of 7:00 AM and 9:00 AM and 3:00
PM and 6:00 PM, Monday through Friday of each week:
Amherst Street
Broad Street
Canal Street
Concord Street
D. W. Highway
East Dunstable Road
East Hollis Street
Kinsley Street
Main Street
6.03 Services, Materials, and Equipment
A. Unless otherwise specified in the General Requirements, CONTRACTOR | shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools,
appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and
incidentals necessary for the performance, testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good
quality and new, except as otherwise provided in the Contract Documents. Ail warranties and guarantees specifically
called for by the Specifications shall expressly run to the benefit of OWNER. If required by ENGINEER,
CONTRACTOR shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and
quality of materials and equipment. All materials and equipment shall be stored, applied, installed, connected, erected,
protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as
otherwise may be provided in the Contract Documents.
6.04 Progress Schedule
A. CONTRACTOR shall adhere to the progress schedule established in accordance with paragraph 2.07 as it may be
adjusted from time to time as provided below.
1. CONTRACTOR shall submit to ENGINEER for acceptance (to the extent indicated in paragraph 2.07) proposed
adjustments in the progress schedule that will not result in changing the Contract Times (or Milestones). Such
adjustments will conform generally to the progress schedule then in effect and additionally will comply with any
provisions of the General Requirements applicable thereto.
2, Proposed adjustments in the progress schedule that will change the Contract Times (or Milestones) shall be
submitted in accordance with the requirements of Article 12. Such adjustments may only be made by a Change
Order or Written Amendment in accordance with Article 12.
6.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name
of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the
type, function, appearance, and quality required. Unless the specification or description contains or is followed by
words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or
equipment or material or equipment of other Suppliers may be submitted to ENGINEER for review under the
circumstances described below.
GC - 20 of 53