STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is dated as of the day of in the year 2020 by and between
the City of Nashua, New Hampshire (hereinafter called OWNER) and Seaicoating, Inc, d/b/a INDUS _and
its successors, transferees and assignees together (hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as
follows:
ARTICLE 1 - WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows:
The work will be at various street locations throughout the City of Nashua and consists primarily
crack sealing.
ARTICLE 3 - ENGINEER
3.01 The Project has been designed by: Division of Public Works
Engineering Departinent
9 Riverside Street
Nashua, NH 03062
who is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties and
responsibilities, and have the rights and authority assigned to ENGINEER in the Contract Documents in
connection with completion of the Work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness
for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Dates for Substantial Completion
The anticipated start date of the contract is on or about May 18, 2020. Project will begin once a
written “Notice to Proceed” is issued. Substantial Completion shall be by August 21, 2020. Completion.
Final Completion shall be by September 30, 2020.