Finance Committee - Agenda - 8/5/2020 - P90

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
90
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

WALDRON ENGINEERING & CONSTRUCTION, INE.

To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Jeremy P. Smith, P.E., Waldron Engineering & Construction, Inc.

Date: July 9" , 2020

Re: Change Order Request Review 023

NWWYTF Energy Recovery Upgrade Project

Attachments: Metimen Construction PCO-023 Remote Status Wiring

Mr. Keating:

Waldron has compiled its review based on review of the Owner’s documentation (design
documents, OEM submittals, submittal reviews, RF] responses, and project notes) and the
Contractor’s documentation (RFI’s, Submittals, Reports, issued Change Orders). Specifically;
Waldron has reviewed the issue of additional work associated with the installation of the jacket
water booster pumps. Methuen has previously submitted for the related electrical scope of work.

Summary Review

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 3 0 0
Original Cost Cost Adjustment Direct Cost Impact Cost Adjustment
claim Assessment Recommended
None $5,171.40 $5,171 35,171

Detailed Review-Base Cost Validity

Methuen has made a claim for the work as required based on RFI responses, submittal reviews
and Field conditions. The claim is based on their work and their subcontractor’s work resulting
from the above. Waldron has reviewed the design documents, OEM submittals, submittal
reviews, and RFI responses regarding this issue. Waldron has relied on vendor quotes, project
cost estimations, historical project data, RS Means, and its own proprietary cost data to review the
cost validity of the work scope.

The submitted PCO is based on additions to the work encountered in the field around a
requirement from Eversource to include a breaker status wired point. The conduit for this already
existed, but new wire had to be pulled in to accommodate this work. This is an extra to the overall
scope of work.